Body

WILMER – The road reconstruction in the City of Wilmer at Beltline Road from the westernmost city limits to Summers Road will continue for the next four to six weeks.

On July 15, Wilmer City Council approved an agreement for the reconstruction of this roadwork approving the terms and conditions of the agreement with Reynolds Asphalt & Construction Company. This was done through the utilization of an Interlocal Agreement with the City of Grand Prairie for the reconstruction.

The cost of the roadwork is not to exceed $768,780 and is part of the fiscal year 2020/2021 budget.

The reconstruction will reconstruct the asphalt surface of Beltline Road. The contractor is removing the existing asphalt pavement and performing compaction of the sub grade prior to the installation of new asphalt pavement, which will provide for a smoother driving experience for vehicles that travel the roadway.